Abstract:
Project test deficiencies frequently occur in cost/schedule driven flight instrument developments. Cost/schedule driven, high-risk instrument projects should plan for expanded test programs. Should engineering problems arise and reserves become depleted, consideration should be given to reductions in mission scope, instead of reductions in the test program. Allow time for retest after correcting problems discovered during testing.