NASA-LLIS-0859
Lessons Learned – Facilities, Complete Contract Specs. Requirements
| contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
| date accessioned | 2017-09-04T18:50:25Z | |
| date available | 2017-09-04T18:50:25Z | |
| date copyright | 08/23/1999 | |
| date issued | 1999 | |
| identifier other | KUTEQCAAAAAAAAAA.pdf | |
| identifier uri | https://lib.yabesh.ir/std/handle/yse/231869 | |
| description abstract | Description of Driving Event: A water line coming into a building was being increased in size to accommodate a new building sprinkler system. The excavation was done, but the compaction that should have been done was not. The specification of backfilling was not part of the contract documents. | |
| language | English | |
| title | NASA-LLIS-0859 | num |
| title | Lessons Learned – Facilities, Complete Contract Specs. Requirements | en |
| type | standard | |
| page | 2 | |
| status | Active | |
| tree | NASA - National Aeronautics and Space Administration (NASA):;1999 | |
| contenttype | fulltext | |
| subject keywords | Administration/Organization | |
| subject keywords | Environment | |
| subject keywords | Facilities | |
| subject keywords | Fire Protection |