NASA-LLIS-1520
Lessons Learned - Check Testbed Health Before Beginning or Resuming Flight System Test (2003)
contributor author | NASA - National Aeronautics and Space Administration (NASA) | |
date accessioned | 2017-09-04T18:37:33Z | |
date available | 2017-09-04T18:37:33Z | |
date copyright | 01/28/2005 | |
date issued | 2005 | |
identifier other | JNWEQCAAAAAAAAAA.pdf | |
identifier uri | https://lib.yabesh.ir/std/handle/yse/219456 | |
description abstract | Abstract: In a scenario that is most likely to occur on severely time-constrained flight projects, system-level testing is interrupted and test time is lost because of unreported changes to the testbed configuration. Use walkthroughs, briefings, startup procedures, and reporting tools to ensure at the beginning of each work shift that test operators are apprised of all changes to the system testbed configuration. | |
language | English | |
title | NASA-LLIS-1520 | num |
title | Lessons Learned - Check Testbed Health Before Beginning or Resuming Flight System Test (2003) | en |
type | standard | |
page | 3 | |
status | Active | |
tree | NASA - National Aeronautics and Space Administration (NASA):;2005 | |
contenttype | fulltext | |
subject keywords | and launch operations | |
subject keywords | assemble | |
subject keywords | ATLO | |
subject keywords | Configuration Management | |
subject keywords | Flight Equipment | |
subject keywords | Ground Equipment | |
subject keywords | Ground Operations | |
subject keywords | Spacecraft | |
subject keywords | subsystem test | |
subject keywords | test | |
subject keywords | Test & Verification | |
subject keywords | Test Article | |
subject keywords | test bed | |
subject keywords | test configuration | |
subject keywords | Test Facility | |
subject keywords | test plan | |
subject keywords | test procedure |